Q: there is a scheduled receipt in week 4 for an item with a two-week lead time. What can be inferred from this information?
a) the MRP grid should show a corresponding planned order release in week 2
b) a firm planned order must have been used to provide more lead time
c) this item has yet to be released
d) the grid should show a corresponding planned order receipt for week 4
a) the MRP grid should show a corresponding planned order release in week 2
b) a firm planned order must have been used to provide more lead time
c) this item has yet to be released
d) the grid should show a corresponding planned order receipt for week 4