1. Power up the control cabinets of ADMS and start pre-com.
2. All agitators running test, Prepare for official commissioning inspection.
3.Monkey board talkback station commissioning.
4.Remote function test of main HPU.
5.Weekly commissioning meeting for the schedule of the coming week.
2. All agitators running test, Prepare for official commissioning inspection.
3.Monkey board talkback station commissioning.
4.Remote function test of main HPU.
5.Weekly commissioning meeting for the schedule of the coming week.