1. Standby for rig transfering
2.BOP system preparation for control power energization(Overall checking)
3. Coordinate design department and CAM to check & confirm the drill floor HPU remote control issues
4. Construction progress and punch status cheking for mud treatment euipments.
2.BOP system preparation for control power energization(Overall checking)
3. Coordinate design department and CAM to check & confirm the drill floor HPU remote control issues
4. Construction progress and punch status cheking for mud treatment euipments.